Purge control link behind bell furnace inner hood


Ready to start


Starting conditions: Cooling control and atmosphere control complete

Step 1: Start flushing


Purge control link behind bell furnace inner hood


Nitrogen large-flow butterfly valve and nitrogen discharge valve are opened. The fan starts low-speed operation and the feedback signal is in place.

Step 2: Flush timing

When N2 purging flow ≥ set value and converter of furnace fan operates normally, PLC timer is started and the inner cover pre-flushing is completed after reaching the set time. If one of these conditions is not met, the timer clears "0".


Step 3: Flush is complete

The butterfly valve with large nitrogen flow is opened, the N2 discharge valve is closed, and the furnace fan stops.

Purge control link behind bell furnace inner hood